Guide · Building a bid

Maximising quality points in public procurement – analysing the award criteria and optimising strategically

In public procurement, quality is not assessed on subjective impressions, brand or marketing communication. When a contracting authority chooses the most economically advantageous bid on the basis of the best price-quality ratio (Procurement Act, section 93), quality has been broken down into award criteria that are announced in advance and measured numerically.

Updated 7 July 2026 · Tendera

A bidding company's success depends on its ability to analyse these criteria systematically and optimise its bid to match them precisely. This article covers the mechanisms for maximising quality points at the bidding stage, lawfully and strategically.

1. The difference between minimum requirements and award criteria

The first step in maximising quality points is to tell two legal concepts apart: the mandatory minimum requirements and the actual award criteria.

A bidder must make sure it does not offer needless over-quality on points defined only as minimum requirements, because that typically raises the price of the bid without a corresponding benefit in the scoring.

2. Analysing the scoring model mathematically

Maximising quality points is fundamentally mathematics and an interpretation of the needs analysis the contracting authority has made. Before writing a single bid document, a company should model the scoring formula in the tender documents.

The ratio of quality to price determines the bidding strategy:

3. Presenting evidence and making quality verifiable

A contracting authority cannot award points for promises, only for verifiable facts. A bidder must be able to demonstrate quality objectively.

4. The contracting authority's discretion and the bidder's response

Case law gives contracting authorities wide discretion in how they apply quality award criteria, as long as they follow the model announced in the tender documents and treat all bidders equally.

This puts the onus on the bidder to raise ambiguities in good time. If the award criteria are unclear, open to interpretation or leave the contracting authority unlimited freedom of choice (a criterion such as "general goodness" with no clarifying scoring matrix), the criterion is probably contrary to the Procurement Act.

A professional bidder uses the clarification questions available during the bidding period. By requiring the contracting authority to specify how quality is scored, the bidder both secures a fair comparison and gains valuable information about what the authority really values and weights.

Frequently asked questions

What are quality points made of?

Award criteria announced in advance and measured numerically (section 93) — technical merit, the qualifications of the experts or environmental impact, for example. Brand and impressions earn no points.

Why is offering over-quality a mistake?

Exceeding a minimum requirement earns no extra points as a rule, unless that is expressly stated. Over-quality raises the price of the bid without a corresponding benefit in the scoring.

How should the scoring model be analysed?

Model the scoring formula before writing the bid. In a quality-weighted model (quality 70 %, for example) it pays to offer the best expertise even at a higher price; in a price-weighted model, optimising the price decides.